Lacamas Comes Back in Stages This Fall, Water First and the Bridge Last

At Round Lake this week, the water sits well below its usual summer line, and a fence cuts across the northeast corner of the park. The legal notice the City of Camas published in September put numbers on the first change. Starting at 8 a.m. on Monday, Sept. 21, 2026, Public Works would bring Lacamas Lake down from about 11 feet to about 5 feet, reaching that level around Monday, Oct. 5. The fence has a different owner and a different deadline.

The lake and the fence are two projects, run by two governments, on two schedules. If you know which is which, you can work out what reopens first and where you can walk in the meantime.

Two Projects, Two Owners, One Park

The low water belongs to the City of Camas. Its Public Works department calls the drawdown of Lacamas Lake and Round Lake an annual event. The lakes are lowered roughly six feet so crews can inspect and repair the dam. This year the city is also replacing parts of the dam "in order to update and improve it, which is why more time is required." The city's notice also warns of "significant trail closures around Round Lake."

The fence belongs to Clark County. In July, county Public Works announced it would replace the aging bridge on the main access road in the park's northeast corner. Every trail segment inside the work area would close while construction was underway. The county's map marks two closed zones. The northeast zone reads "Trails closed 8/1 - 11/15." A small patch beside the dam on the southwest side of Round Lake reads "Trails closed 9/15 - 11/15."

The two agencies describe the dam area a little differently. The county's July text says trails near the dam would stay open, with city flaggers guiding walkers whenever equipment moves. The same notice's map marks that small area closed through Nov. 15. The posted signs on the ground settle it on any given day.

The lake had already been busy before either fence went up. The city's lake management page announced closures of the Leadbetter boat ramp on July 22 and again on Aug. 21, 2026, so that contractors from Aquatechnex could carry out scheduled alum treatments meant to reduce harmful algal blooms in Lacamas Lake. That work falls under the Lacamas, Round and Fallen Leaf Lakes management plan, which the Department of Ecology approved in late 2025. So the summer, the fall drawdown and the bridge work have each kept a different part of Lacamas out of normal use this year.

This Year's Low Water Started Later and Runs Later

The drawdown is routine. What stands out in 2026 is the timing. Here are the city's announced dates from recent years, as reported in the Camas-Washougal Post-Record:

Year Drawdown begins Minimum level Refill scheduled
2021 Mon., Sept. 13 Around Sept. 27 Oct. 25
2023 Mon., Sept. 11 Mon., Sept. 25 Oct. 25, tentative
2024 Mon., Sept. 16 Through Fri., Sept. 27 Oct. 28, tentative
2026 Mon., Sept. 21 Around Mon., Oct. 5 Nov. 2

In each of the earlier years, the lake reached its low point in the last week of September and the refill was due in the last week of October. This year everything moved back. The low point came about a week later, and the refill is scheduled to start in November for the first time in this run of notices. The 2024 Post-Record notice set the minimum level through Sept. 27 and a refill around Oct. 28. In 2026, the low point was scheduled for around Oct. 5 and the refill for Nov. 2. The city's notice ties the extra time to this year's work replacing dam parts.

The refill still depends on the weather. The city expects it to take "several weeks, depending on rainfall volumes." A Nov. 2 start means the shoreline will look low well into November even if crews finish on time.

Why the Bridge Sat Quiet Through September

If you walked past the northeast fence in September and saw no one working, there was a reason. The bridge has to go back in on a schedule set by environmental permits, not by the calendar.

The old crossing was built from two repurposed rail cars. Years outdoors had rusted and corroded them. The bridge was still considered safe for people on foot, but the county worried it could collapse under the weight of a work truck. Evelyn Ives, a project manager with the county's parks and lands division, explained this to The Columbian. The replacement is a prefabricated steel structure with a concrete deck. It will be 12 feet wide, where the old bridge was about 20, and 5 to 10 feet longer on each side of the creek.

The delay comes from the order the work had to happen in. The county's Sept. 18 update says the old bridge came out in August because that was the permitted window for in-water stream work. After that, foundation design calculations needed review before crews could return to the site. Ives told The Columbian that the quiet weeks were the contractor working through submittals, the routine requests for materials and equipment. She said those are separate from permits. Her account of the sequence:

"In a normal situation, we probably would have just delayed the start date. Because of our environmental permits, we had to do the removal and the demo and the in-water work … in the work window."

According to the same Columbian report, Nutter Corp. won the construction contract with a bid of $485,000, against an engineering estimate of $811,000. Design, survey, permitting and permit fees bring the total to more than $1 million, and Ives said the project was running about $70,000 under budget. The bridge was originally expected by Nov. 15 and is now likely to finish in late November or early December. The Post-Record reported on Oct. 8 that the northeast trails were still closed.

This bridge matters more than its size suggests because of where it sits. Ives told The Columbian there "isn't really a safe detour" around it. A local resident quoted in the same piece said the construction site "bisects the park," so cyclists who used that route to cross town safely have lost it for now. The Columbian also reported that fencing on one closed trail was cut down so often that the contractor eventually left that trail open. The county still asks visitors to stay out of work areas whether or not crews are on site.

The Order Things Come Back

Taken together, the two projects give a fairly clear reopening sequence. Every date below is a schedule or an estimate, not a confirmed finish:

  1. Nov. 2: The city's published date to begin refilling Lacamas Lake. It is expected to take several weeks, depending on rain.
  2. Nov. 15: The end date printed on the county map for the dam-area closure southwest of Round Lake. It was also the bridge's original finish date.
  3. Late November or early December: The revised estimate for the new bridge, according to The Columbian's Oct. 2 report. Until it is done, the northeast trails stay closed and the park cannot be crossed through the middle.

So the lake starts coming back before the trails do, and the crossing that links the two halves of the park will probably be the last piece to reopen. The county has said it will post schedule changes on its Lacamas Regional Park page. The city's drawdown notice is the place to check for the lake.

Walking Lacamas in the Meantime

The park itself remains open. Lacamas Regional Park is at 3344 NE Everett St. and is open from 7 a.m. to dusk, which the county defines as half an hour after sunset. It has 26 parking spaces plus one accessible stall. With the clocks changing on Nov. 1, dusk will come early, so the county's closing time arrives sooner in the afternoon than it did in September.

Across its 312 acres, the park has about 9.5 miles of gravel and dirt trails. They connect to the Lacamas Heritage Trail along the south shore of Lacamas Lake. At the other end of the lake, the city's Heritage Park, at 303 NE Lake Road, has a boat launch and the trailhead for the lakeside path.

Walking routes in the park usually cross the Round Lake dam and continue toward Pothole Falls and Lower Falls, with a side loop through the Camas lily fields. The work this fall sits on or near those routes, so check the signs at the trailhead before you plan a loop around them. The county's own map notes that "unmarked trails exist" and that it is for reference only. The lily bloom, the park's best-known photo moment, is in mid-April. If the county's estimate holds, the new bridge will have been open for months by then.

If you live near Lacamas and want to know how projects like this one affect a sale or purchase close to the park, Oxford Street Partners is glad to talk it through. Leigh and Harvey follow these Camas schedules closely, from the refill date to the bridge opening, so you can time your plans around them. Book a Consultation whenever it suits you.

Work With Us

Are you seeking your own British agent to have at your service? Stop right here! Introducing the Oxford Street Partners, a real estate team with Cascade Hasson Sotheby's International Realty—the joined forces of Leigh Calvert and Harvey Coker, two Brits offering first class real estate services in the SW Washington region.